Temporary Works: What Counts, Who's Responsible and What to Document

What counts as temporary works, who is responsible under CDM 2015, whether you need a temporary works coordinator and what to write into your RAMS.

10 min read
Write this RAMS freeNo signup · about 2 minutes
Blog header image for Temporary Works: What Counts, Who's Responsible and What to Document

Does the trench box you hired for a drainage run count as temporary works? What about the props holding up a wall while you knock through for a new opening, or the hoarding round the front of the site? And if they do, who on a small job is meant to be checking them?

Temporary works are one of those subjects that sound like they belong to big civils jobs with an engineer on site. They don't. If you prop, shore, support or put up something for people to stand on, you're already doing temporary works. The question is whether you're managing them, or just hoping they hold.

Key takeaway: if something is there to hold up, hold back or give access during the job, treat it as temporary works. Get a design that fits the actual loads, check it's built to that design before it's used, inspect it, and control when it comes out. Then write each of those steps into your RAMS.

What are temporary works?

HSE's temporary works guidance describes them as an engineered solution used to support or protect a structure, plant or equipment, or the sides of an excavation, or to provide access during construction. HSE's examples include:

  • Shoring and trench support for excavations
  • Propping for walls and floors
  • Falsework for concrete pours above ground
  • Scaffolds
  • Haul roads and working platforms for plant, including cranes
  • Permanent works used temporarily, such as a floor slab taking plant loads before the building is finished
  • Site fencing, hoarding, welfare and office units
  • Earthworks such as stockpiles that will be removed later

What does the law say about temporary works?

HSE's own page is clear that there are no specific legal requirements on how temporary works should be managed. That's left to each organisation. What the law does set is the outcome.

The Construction (Design and Management) Regulations 2015, regulation 19 covers stability of structures. In plain terms:

  1. All practicable steps must be taken to stop a new or existing structure collapsing where the work may leave it unstable or in a temporary state of weakness.
  2. Any buttress, temporary support or temporary structure must be designed, installed and maintained to withstand any foreseeable loads, and only used for the purpose it was designed and installed for.
  3. A structure must not be loaded so that it becomes unsafe.

CDM 2015's definitions matter here too. A "structure" expressly includes formwork, falsework, scaffolds and other structures used for support or access during construction work. A "designer" is anyone who prepares or modifies a design relating to a structure. Read together, the person designing your propping or trench support is a designer under CDM 2015, with the same duty to eliminate, reduce or control foreseeable risks. Our CDM 2015 guide covers those duties in more detail.

On a job with more than one contractor, the principal contractor must plan, manage and monitor the construction phase (regulation 13), and every contractor must plan, manage and monitor their own work (regulation 15). HSE's temporary works FAQs put it simply: the legal duty sits with the party in control of the work.

Reference table: common temporary works and the inspection rules

  • Trench support and shoring. Rule: CDM 2015 regulation 22. Before work in a supported excavation, a competent person inspects at the start of every shift, after any event likely to affect its strength or stability, and after any accidental fall of material.
  • Cofferdams and caissons. Rule: CDM 2015 regulation 23. Inspected by a competent person at the start of every shift and after any event likely to affect strength or stability.
  • Scaffolds and other working platforms with a fall of 2 metres or more. Rule: Work at Height Regulations 2005, regulation 12. Inspected in position before use and within the previous 7 days, with a written report.
  • Props, needles, falsework and formwork. Rule: CDM 2015 regulation 19. Designed for foreseeable loads, used only as designed, and maintained. Follow the manufacturer's instructions for proprietary kit.
  • Hoarding, fencing, haul roads and crane bases. Rule: CDM 2015 regulation 19. Same duty: designed for the loads they'll really see, used only as intended.

Do you need a temporary works coordinator?

Not by law. HSE's FAQs say there's no legal requirement to use the title "temporary works coordinator" (TWC) or the process set out in BS 5975, the British Standard for temporary works procedures. HSE's guidance points to BS 5975-1:2024, which covers management procedures. HSE describes the standard as industry consensus on good practice and says the approach works well on medium and large projects.

That said, HSE also calls appointing a TWC an effective way of making sure designs are prepared, checked and correctly erected. If you appoint one, HSE says they should be:

  • Formally appointed, with enough authority to do the job
  • Able to stop work that isn't satisfactory
  • Involved in planning where and when temporary works are needed, not just checking a drawing

On complex projects the TWC is often a chartered civil or structural engineer based on site. On simpler jobs, HSE says the main contractor may take on the role and get engineering advice when it's needed. And on projects with simple temporary works needs, you may choose not to appoint a TWC at all. HSE is clear you still have to make sure temporary works are properly managed. Dropping the job title doesn't drop the job.

How to manage temporary works on a small job

This is where most small contractors can tighten up without adding much paperwork. A workable routine looks like this:

  1. List them. Keep a simple temporary works register: each item, who designed and checked it, who put it in and when it was last inspected. A side of A4 is fine on a small site.
  2. Get a design that fits. HSE says that, except in the simplest situations, temporary works need a design with calculations, and more complex works need the design checked independently. HSE also says not every structural engineer can design temporary works; the designer needs temporary works training and experience. For hired kit such as trench boxes and props, follow the manufacturer's instructions.
  3. Brief the designer properly. Tell them about ground conditions, plant tracking nearby, materials stacked at the edge and the build sequence. HSE notes that temporary works failures often come down to loads being underestimated, especially side loads.
  4. Check before loading. Before anyone loads it, someone competent confirms it's built to the design. Many sites record this with a "permit to load".
  5. Inspect it. Use the intervals in the table above as the minimum, and add checks after heavy rain, frost, strikes from plant or anything else that could disturb it.
  6. Protect it from other trades. HSE warns that temporary works are easily affected by other work nearby, such as an excavator tracking alongside a trench.
  7. Control removal. Nothing comes out until the permanent works can carry the load. Many sites use a "permit to strike" or "permit to dismantle" for this.

If you're unsure who on your team is competent to check or inspect, our guide to the competent person in health and safety sets out what that means in practice.

Where temporary works belong in your RAMS and paperwork

Temporary works touch several documents. The trick is to make sure each one says something specific, rather than copying "temporary works to be managed in accordance with BS 5975" into everything.

  • RAMS for the task. The sequence for installing, using and removing the temporary works, who is competent to do each step, exclusion zones, hold points (no loading until checked), the inspection regime and what to do if something moves or gets damaged. See our guides to RAMS for excavation and trenching and RAMS for scaffolding.
  • Construction phase plan. Who coordinates temporary works across the project and how the register is kept. Our construction phase plan guide covers what the plan needs to include.
  • Permits to work. A dig permit before breaking ground, and your own hold-point permits for loading and striking. The permit to work guide explains how permits fit alongside a RAMS rather than replacing it.
  • Inspection records. Excavation and working platform inspections, with dates and the inspector's name.

None of these documents holds up a trench wall on its own. They record decisions that people on site still have to carry out.

Getting temporary works into your documents faster

swiftRMS writes RAMS, method statements, construction phase plans and safe systems of work for UK contractors. Describe the job (a drainage run in a trench box, a knock-through with props, a scaffold for a roof repair) and AI RAMS drafts the installation sequence, hold points, inspection regime and removal steps into the method statement in minutes. Digital permits to work, including dig and general permits, sit alongside the RAMS so the go and no-go points are recorded on site.

swiftRMS doesn't design temporary works or produce calculations. That still needs a competent temporary works designer. Everything swiftRMS produces is an AI-generated draft, and a competent person must review it, check it against the real site and sign it off before work starts.

Try swiftRMS free and generate a RAMS for your next job with temporary works. No card needed.

Frequently asked questions

What counts as temporary works?

HSE describes temporary works as an engineered solution used to support or protect a structure, plant, equipment or the sides of an excavation, or to provide access during construction. Common examples are trench support, propping, falsework, formwork, scaffolds, crane bases, haul roads, hoarding and welfare units.

Is a temporary works coordinator a legal requirement?

No. HSE says there is no legal requirement to use the temporary works coordinator title or the BS 5975 process. HSE still describes appointing one as an effective approach, especially on medium and large projects. On simpler jobs you can manage temporary works another way, but you must still make sure they are properly managed and safe.

Who is responsible for temporary works on site?

HSE says the legal duty sits with the party in control of the work. Under CDM 2015, the principal contractor must plan, manage and monitor the construction phase and every contractor must do the same for their own work. Whoever designs temporary works is a designer under CDM 2015, with duties to reduce foreseeable risks.

How often do temporary works need inspecting?

It depends on the item. Supported excavations, cofferdams and caissons are inspected by a competent person at the start of every shift and after events affecting stability. Working platforms with a fall of 2 metres or more must have been inspected within the previous 7 days. Add checks after bad weather, plant strikes or changes.