Risk Assessment Matrix: How to Use a 5x5 Matrix (UK)

How a 5x5 risk assessment matrix works: likelihood x severity, scoring before and after controls, 3x3 vs 5x5, worked UK site examples and common mistakes.

13 min read
Write a risk assessment freeNo signup · about 2 minutes
UK site manager in hi-vis reviewing a printed risk assessment on a clipboard at a construction site

A risk assessment comes back from a subcontractor with every hazard scored 4. Slips, falls from the roof edge, dust, the lot. Nobody's thought about it. They've just filled in the box. If you've checked RAMS for any length of time, you've seen it. The risk assessment matrix is meant to stop that happening, but only if the people using it understand what the numbers mean.

A risk assessment matrix is a grid that rates a hazard by two things: how likely it is to cause harm (likelihood) and how bad that harm would be (severity). Multiply the two together and you get a risk rating. On a 5x5 matrix both scales run from 1 to 5, so scores run from 1 to 25. You score each hazard before controls, apply your controls, then score it again to show the residual risk. The score helps you rank what to deal with first. It doesn't replace thinking about the hazard.

This guide covers how the 5x5 matrix works, worked scoring examples from UK sites, when a 3x3 might be enough, and the mistakes that get assessments sent back by principal contractors and questioned by inspectors.

What is a risk assessment matrix?

It's a scoring tool, nothing more. The law in Great Britain requires a "suitable and sufficient" assessment of the risks to your workers and anyone else affected by your work. That comes from regulation 3 of the Management of Health and Safety at Work Regulations 1999. The matrix is one of several ways to show how you judged the level of risk.

If you're not clear on the difference between hazard and risk, it matters here. A hazard is the thing that can cause harm, like an unprotected edge. Risk is the chance of harm happening combined with how serious it would be. Our guide to hazard vs risk goes into this properly, but the short version is that the matrix scores risk, not hazards.

Does HSE require a risk matrix?

No. HSE's guidance on the steps needed to manage risk tells you to decide how likely it is that someone could be harmed and how seriously. It doesn't prescribe a scoring method or a grid. You can meet the legal duty with a written judgement of high, medium or low, as long as the assessment is suitable and sufficient for the work.

In practice, most UK principal contractors, main contractors and FM clients expect a numerical matrix in RAMS, and 5x5 is the most common. So it's worth getting right, even though it isn't a legal requirement in itself.

How the 5x5 risk assessment matrix works

You score each hazard on two scales. The exact wording varies between companies, so always use the definitions your organisation or principal contractor has set. A typical version looks like this.

Likelihood (1 to 5)

  • 1 Very unlikely: could happen, but you'd be surprised. No history of it in this type of work.
  • 2 Unlikely: could happen occasionally. It's happened in the industry, but rarely.
  • 3 Possible: could happen at some point during the job. You've seen it happen.
  • 4 Likely: will probably happen if nothing changes.
  • 5 Very likely: expected to happen, or already happening.

Severity (1 to 5)

  • 1 Negligible: no injury, or a minor one needing first aid only.
  • 2 Minor: injury or ill health causing a short absence from work.
  • 3 Moderate: injury leading to more than seven days off work, which would be reportable under RIDDOR.
  • 4 Major: serious injury such as a fracture, amputation or loss of sight, or serious ill health.
  • 5 Catastrophic: a fatality, or multiple serious injuries.

Tying the severity scale to RIDDOR categories is a useful habit. It gives assessors a fixed reference point instead of a vague sense of "quite bad". Our RIDDOR reporting guide sets out which injuries fall into which category.

Reading the grid

Picture a grid with likelihood running up one side and severity along the bottom. Each of the 25 cells holds the product of its row and column. The bottom-left cell is 1 (very unlikely, negligible). The top-right is 25 (very likely, catastrophic). Some numbers can't appear at all: there's no way to make 7, 11, 13 or 14 by multiplying two numbers from 1 to 5.

The cells are then grouped into bands, usually colour coded green, amber and red. One common banding is:

  • 1 to 4, Low: acceptable with existing controls. Monitor.
  • 5 to 9, Medium: reduce further if reasonably practicable. Supervisor keeps an eye on it.
  • 10 to 16, High: additional controls needed before work starts. Senior sign-off.
  • 20 to 25, Very high: don't start, or stop work, until the risk is reduced.

Your company might draw the lines differently, and that's fine. What matters is that everyone scoring RAMS on your sites uses the same bands and knows what action each band triggers.

Scoring risk before and after controls

Every hazard in a RAMS should carry two scores. The initial (or inherent) risk is the score with no specific controls in place. The residual risk is the score once your controls are actually applied on site.

The gap between them shows the reader that your controls do something. It also forces you to be honest. If the residual score is still high, either your controls aren't good enough or the work needs a different method.

Choose controls by working down the hierarchy of control: eliminate the hazard if you can, then substitute, then use engineering controls, then procedures, and PPE last. Controls higher up the hierarchy usually cut the score far more than a line saying "operatives to take care".

Worked example: fragile rooflights on an industrial unit

A roofing contractor is replacing damaged sheets on a low-pitched warehouse roof in the Midlands. The roof has fragile rooflights spaced along its length.

Initial risk. Walking the roof with no protection, a fall through a rooflight is likely over a multi-day job. Likelihood 4. A fall through a fragile surface onto a concrete floor several metres below could kill. Severity 5. Score 4 x 5 = 20, very high. Work can't start like this.

Controls. Work from a MEWP where the sheet positions allow it. Where operatives must go onto the roof, fit rooflight covers suitable for the loads involved, install edge protection at the eaves, and rig safety netting below the work area. A permit controls roof access, and a named supervisor checks the covers before each shift.

Residual risk. With covers and nets in place, a fall through a rooflight becomes very unlikely. Likelihood 1. The netting also reduces the consequence if someone does fall, because it arrests the fall well above the floor. Severity drops to 3. Score 1 x 3 = 3, low.

Notice the severity changed only because one control, the netting, changes what happens in a fall. That's the test. If a control only makes the event less likely, the severity score should stay where it was. Our guide to RAMS for working at height covers the method statement side of this job.

Worked example: wet floors in a shopping centre

A cleaning contractor machine-scrubs a mall concourse. The initial risk of a shopper or member of staff slipping is likelihood 4 during trading hours and severity 4, because a fall on a hard floor can break a wrist or hip. Score 16, high.

Controls: move scrubbing to before opening, use a scrubber-dryer that leaves the floor near dry, cone off the wet section, and keep a second operative on spill response. Residual likelihood 2, severity still 4. Score 8, medium. The severity didn't move because none of the controls changes how hard the floor is. RAMS for cleaning contractors usually follow this pattern.

Worked example: a door supervisor refusing entry

At a busy town-centre bar on a Saturday night, a door supervisor refuses entry to an intoxicated customer. Initial risk of assault: likelihood 4, severity 4. Score 16, high.

Controls: SIA-licensed staff with conflict management training, body-worn video, radios linked to CCTV and the rest of the door team, a clear refusals policy, and never working the door alone at peak times. Residual likelihood 3, severity 4. Score 12, still high.

That's an honest result. Some risks stay high even with sensible controls, and the matrix should say so. It then becomes a management decision whether the controls are enough or more is needed, such as extra staff at closing time. Your door supervisor RAMS should show that thinking rather than hide it behind a low number.

3x3 vs 5x5 risk matrix: which should you use?

A 3x3 matrix scores likelihood and severity from 1 to 3, giving nine cells and scores from 1 to 9. A 4x4 also exists but is less common in UK construction.

When a 3x3 is enough

  • Low-risk environments such as offices, shops and simple FM tasks.
  • Small businesses with a short list of familiar hazards.
  • Teams new to risk assessment, where simple categories get used consistently.

When a 5x5 is the better choice

  • Construction, demolition, security and maintenance work where outcomes range from a cut finger to a fatality.
  • Where you need to separate similar risks to decide which to deal with first.
  • Where a principal contractor or client specifies it in their RAMS requirements, which many larger ones do.

The trade-off is simple. A 5x5 gives finer distinctions but invites false precision. Arguing over whether a hazard is a 3 or a 4 on likelihood usually means the definitions need tightening, not that the maths matters. A 3x3 used carefully beats a 5x5 filled in out of habit.

Common risk assessment matrix mistakes

These come up again and again when RAMS are rejected. Several of them overlap with what HSE inspectors look for in risk assessments.

Scoring backwards from the answer

Someone decides the residual score "should" be low, then picks numbers to get there. You can spot this when every residual score is 4 or below, whatever the hazard.

Dropping the severity without a reason

Most controls reduce likelihood. Very few reduce severity. If a sheet shows a fall from height going from severity 5 to severity 2 because a toolbox talk was given, it's wrong.

Treating the score as the assessment

A number on its own tells nobody what to do. The value is in the controls column. A reviewer should be able to read the controls and understand why the score dropped.

Controls that aren't on site

The residual score assumes the controls are in place. If the RAMS says netting will be installed and the nets haven't arrived, the real risk is the initial score, and the work should wait.

Different assessors, different scales

One supervisor's "possible" is another's "likely". Print your definitions on the matrix itself, and use the same matrix across all your RAMS.

Missing health risks

Matrices are built around accidents, so long-term health risks get scored low because nothing happens today. Silica dust, noise, hand-arm vibration and asbestos cause harm over years. Score severity on the eventual ill health, not on what happens this afternoon. Hand-arm vibration syndrome, for example, can cause permanent damage long after the job has finished.

Never re-scoring

Conditions change. Weather, a change of method, a different crew or a live area next door can all shift the likelihood. Under regulation 3(3) of the 1999 Regulations, the assessment must be reviewed if there's reason to suspect it's no longer valid, or if there's been a significant change in the matters it relates to.

Who should score the matrix?

The person doing the assessment needs enough knowledge of the work and its hazards to make sound judgements. That's a competent person, and regulation 7 of the 1999 Regulations requires employers to appoint one or more competent persons to help them meet their health and safety duties. On a live site, the scoring should also involve the people who do the work. They know where the job goes wrong.

How swiftRMS helps

swiftRMS is AI RAMS software that drafts risk assessments and method statements for UK construction, security and FM teams. When you describe a task, it drafts the hazards, the controls and a 5x5 likelihood x severity rating for each hazard, before and after controls. You can see the format in our example RAMS.

The ratings are a starting point for review, not a verdict. The draft doesn't know your site, your crew or what's happening in the next bay. A competent person should check every rating against site conditions, change anything that doesn't fit, and approve the document before it's used. If your company has its own matrix bands, the reviewer should check the draft scores against them. Our risk assessment software page explains how drafting and review fit together.

Want to see how it scores a real task? Describe a job you've got coming up and get a free RAMS preview, with no signup, at app.swiftrms.co.uk/try. If it's useful, there's a 14-day free trial with no card needed.

Frequently Asked Questions

What is a 5x5 risk assessment matrix?

It's a grid that scores a hazard from 1 to 5 on likelihood and 1 to 5 on severity. Multiplying the two gives a risk rating from 1 to 25. The ratings are grouped into bands such as low, medium, high and very high, and each band tells you what action to take. Many UK construction RAMS use this format.

How do you calculate a risk rating?

Multiply the likelihood score by the severity score. A hazard that's likely (4) with a potentially major outcome (4) scores 16. Do it twice, once before controls and once after, so the reader can see what your controls achieve.

Is a risk matrix a legal requirement in the UK?

No. The Management of Health and Safety at Work Regulations 1999 require a suitable and sufficient risk assessment, and employers with five or more employees must record the significant findings. Neither the regulations nor HSE's guidance on the steps to manage risk require a scoring matrix. Many clients and principal contractors do ask for one in their RAMS requirements, though.

What is an acceptable residual risk score?

There's no legal number. The legal test is whether you've reduced the risk so far as is reasonably practicable, which means weighing the risk against the time, cost and effort of further controls. Many companies treat residual scores of 1 to 4 as acceptable and anything in the high band as needing senior review, but check your own policy and your client's requirements.

Should severity change after controls?

Only if a control changes the outcome of the event. Safety netting, guarding that limits contact, or a lower working height can reduce severity. Training, signage and supervision usually reduce likelihood only, so the severity score should stay the same.

Is a 3x3 or 5x5 matrix better?

A 5x5 suits higher-risk work like construction and security, where outcomes vary widely and you need to rank risks. A 3x3 is often enough for low-risk workplaces such as offices. The best matrix is the one your team uses consistently, with clear definitions.